Orlando Utilities Company Reliable Plaza, Orlando, Florida Project Details
OUC Parking Lot had a total of 19 slab on grade pours totaling 381,199 SF. Each pour ranged from 545 cubic yards to 940 cubic yards of concrete. CCK was able to place and finish on average 120 yards of concrete an hour for this project.
Project
OUC Reliable Plaza
Orlando, Florida
Owner
Orange County Utilities
CM/GC
JCB Construction
A/E
GAI Consultants
Value
$1,400,000
Substantial Completion
Started on April 18, 2011 and Completed on September 22, 2011
Materials:
- 9,807 cubic yards of Concrete.
- 22 tons of Rebar was installed.