Fontainebleau Miami Beach, Lapis Spa Project Details

CCK Construction Services, Inc. was selected as the concrete contractor to provide self-perform services for the renovation and expansion of the Fontainebleau ballroom and spa.

Project

Fontainebleau Miami Beach
LapisTM Spa™
Miami, Florida

Owner

Fontainebleau Resorts, LLC

CM/GC

Turnberry Construction, Inc.

A/E

HKS
Dallas, Texas

Value

$11,300,000

Substantial Completion

July 2008

Project Data

  • 2 story, 220,000sf post-tensioned concrete beam and deck hotel ballroom and spa addition
  • Replicated historically significant staircase and awning design including a 4 story double helix tower
  • Worked through challenging site conditions to facilitate environmental concerns
  • Partnered with general contractor to minimize the impact of a modified schedule as a result of heightened environmental concerns

Material Totals

  • 15,000 cubic yards of concrete
  • 1,500 tons of rebar
  • 1,300 LF of post-tensioning cable, total weight 105,000 lbs