Disney’s Art of Animation Resorts, Lake Buena Vista Project Details
CCK Construction Services, Inc. was selected as the concrete contractor to provide self-perform services for the Disney’s Art of Animation Resorts.
Project
Disney’s Art of Animation Resorts, Lake Buena Vista, FL
Owner
Walt Disney Imagineering
CM/GC
Hardin Construction Company, LLC
A/E
KBJ Architects, Inc
Value
$12,800,000
Substantial Completion
July 2011
Project Data
- 110,000 sfca decks and walls
- 95% of production in 7.5 months
- Foundations and UG MEP only first 6 weeks
- Core decks dependent on load bearing CMU only last 4 weeks
Material Totals
- 39,080 cubic yards of concrete
- 3,692 tons of rebar
- 90,000 sf of Deck Forms at peek
- 21,000 sf of Wall Forms at peek